Adani’s Aust.Coal project unviable:US report

Gautam Adani

By News Desk

SYDNEY, 26 November 2013: India’s energy giant Adani Group has come under the cloud after a new report released today by the US-based Institute for Energy Economics and Financial Analysis (IEEFA) — Remote Prospects: A financial analysis of Adani’s coal gamble in Australia’s Galilee Basin — warns investors the controversial 60 million tonne per annum Carmichael coal mine and infrastructure project is uncommercial.
Report co-author, IEEFA’s Tom Sanzillo, former first deputy comptroller of New York said, “Our conclusion is that Carmichael presents a picture of unacceptable risk. It’s a high cost coal product in a low cost market in structural decline. The project is uneconomic by any measure,” said Mr Sanzillo.
“This project is on the wrong side of the coal boom. It might have been viable 5 years ago but the market has moved on. Adani bought in at the peak of the coal cycle but failed to predict the structural decline of coal,” Mr Sanzillo said.
“Adani is now overextended with unrealistically ambitious expansion plans, has no successful history of coalmining, has lost share value in critical segments, and is overleveraged, with $US12bn of debt against external market capitalisation of $US5.17bn. It is in not in a strong position to complete this project.”
Adani Enterprises is proposing to develop the 60 million tonne per annum thermal coal mine complex in the remote Galilee Coal Basin, central Queensland, Australia; construct 500km of rail infrastructure across agricultural land and floodplains to the coast; and develop a highly contentious coal export terminal through the iconic, UNESCO World Heritage listed Great Barrier Reef.
Key findings of the report include:
The estimated cost of production of A$87/t (energy adjusted) is likely to be above the global thermal coal price for the foreseeable future, rendering the project uneconomic.
Adani is in a weak financial position to execute such an ambitious project: with external equity market capitalisation at only US$5.17bn against estimated net debt of $12bn, development costs for the Carmichael and Abbot Point T0 coal terminal projects are estimated at US$10bn.
Adani has over-estimated coal quality while under-estimating costs and project complexities. At peak production of 60 million tonnes per annum, Adani’s Carmichael mine would be by far the largest coal mine in Australia in a remote inland region with no power, rail, water or workforce infrastructure. Prior to 2013, Adani’s only other experience in coal mining is a 2–4mtpa coal mine in Indonesia that has consistently performed below expectations.
The project is plagued by delays that continue to squeeze the Adani Group’s cash flow, with the company conceding the 2014 timetable for commencement of production has been pushed out to 2016, but more likely 2017 with full production beyond 2022.
Report co-author Tim Buckley, independent financial analyst said, “Our analysis shows a systemic problem with the financial viability of coal mining in the Galilee Basin. Adani may have thought they
were buying a coal mine, but it is increasingly likely that they have inadvertently bought themselves the world’s most expensive cattle station.”
“The Queensland government’s recent announcement of a royalty holiday for the first movers in the exploitation of Galilee coal signals to the market that these high-cost greenfield projects in Queensland are unviable from an investment perspective.”
Erland Howden, Energy Campaigner Greenpeace Australia Pacific, which commissioned the report, said, “It is clear that the Carmichael project, if developed, will be an environmental and climate disaster. This report shows that the project is also uneconomic.”
Adani Australia was contacted to get their response to the report and by an Email it said, ” Adani Mining will be a long term player in Australia and has complete confidence in the viability of the pipeline projects it is currently developing, including the Carmichael Coal and Rail Project, and the expansion of the Abbott Point Coal terminal.”
“In the short to medium-term these projects will create many thousands of jobs and generate significant flow of economic benefits”
” The motivation at the heart of these reports is short-sighted, vested interests that ignore the long-term fundamentals that underpin Adani’s projects in the Galilee Basin and the development of the country at large,” the response said.

16336526731883929
Neeraj Nanda

Share to

Share on facebook
Share on twitter
Share on linkedin
Share on reddit
Share on email
Tags

Get our Newsletter and e-Paper

Related Articles

Police investigate Tarneit shooting involving 3 Indians

Police investigate Tarneit shooting involving 3 Indians

Attacks on health care in Gaza Strip unacceptable, says WHO

Attacks on health care in Gaza Strip unacceptable, says WHO

Astronomy : A Sharper look at the first image of a Black Hole

Astronomy : A Sharper look at the first image of a Black Hole